From: "Osalbo, Faustino Jun" <fosalbo@oaklandnet.com>
 Date: November 3, 2004 3:35:30 PM PST
 To: 'Mark Brest van Kempen' <mbvk@sbcglobal.net>
 Cc: "Brooks, Desley" <DBrooks@oaklandnet.com>, "Nadel, Nancy" <NNadel@oaklandnet.com>, "Uzegbu, Marcel" <MUzegbu@oaklandnet.com>,  "Estes, Lesley" <lcestes@oaklandnet.com>, "Schwarz, Alison" <aschwarz@oaklandnet.com>, khl@rb2.swrcb.ca.gov, "Neary, Mike" <mjneary@oaklandnet.com>, Office of the Mayor <OfficeoftheMayor@oaklandnet.com>, chiye@cazuma.com
 Subject: RE: Leona Quarry silt remains in creek
 
 Mark,
 DeSilva Construction has contracted with Pacific States to install another filter system and the equipment should be in line by the end of next week. This filter system has been discussed this morning and will be explained to RWQB this afternoon.
 The only other system that DeSilva Construction could do is pumping the dirty water into the baker tanks and use the water for site watering. This operation has been in progress since Saturday, Oct. 30th.
 Jun